Sun Streams II is a 200-megawatt solar facility and was completed in June 2021, ahead of schedule and under budget. Across an over 1,000-acre site, McCarthy installed more than 450,000 First Solar Series 6 modules, 5,805 NEXTracker trackers, 5 SMA MWPS-4000 inverter skids, DC wiring and combiner boxes, as well as underground 34.5 kV AC collection wiring.
9 miles
of underground utilities self-performed
792 drilled
piers
54,000 cubic yards
of structural concrete self-performed
1.1 million
work hours
![Longroad Sun Streams II solar modules in dirt field](/sites/default/files/styles/full_width_slide_sm_mobile_1x/public/2023-04/First-Solar-Sunstreams-II-113.jpg?h=9782657d&itok=vhdDEeth)
![Longroad Sun Streams II solar plant infrastructure](/sites/default/files/styles/full_width_slide_sm_mobile_1x/public/2023-04/First-Solar-Sunstreams-II-118.jpg?h=9782657d&itok=74Zu9XdP)
![Longroad Sun Streams II solar power plant infrastructure](/sites/default/files/styles/full_width_slide_sm_mobile_1x/public/2023-04/First-Solar-Sunstreams-II-120.jpg?h=9782657d&itok=Leteuwp1)
Awards and Recognition
2022 Best Project, Energy/Industrial
ENR Southwest
EPC CONTRACTOR
McCarthy Building Companies