McCarthy Tops Out on Banner Gateway Medical Center Tower Expansion Project
$243 million expansion and renovation project marked a major construction milestone and continues on an accelerated schedule towards completion.
McCarthy recently marked the topping-out of the $243 million, 310,000-square-foot Banner Gateway Medical Center Tower expansion project, which is located at 1900 N. Higley Road in Gilbert, Ariz. The expansion essentially doubles the size of the medical center campus, addressing growing needs for women’s services and cancer care by bringing an additional patient tower, an expanded diagnostics and treatment area, and more parking.
The topping out signifies the placement of the last beam atop the new 5-story patient tower. The tower, which is the second on the campus, is a 198,000-square-foot addition that will initially bring 109 new patient beds to the facility. It will also allow for increased capacity of patient beds by an additional 190 total beds once the shelled space is built out to serve the rapidly growing East Valley. The project also includes a three-level, 112,000-square-foot expansion to the Diagnostics and Treatment building, including an expansion of the Emergency, Surgery, Imaging, Cardiopulmonary, and Endoscopy departments.
“Our commitment to serving the health care needs of our community is unwavering and we are pleased to be expanding to meet community growth and the increased demand as a destination center for women and infant services, cancer care and high-quality medical care,” said Lamont Yoder, CEO of Banner Gateway Medical Center and Banner MD Anderson Cancer Center. “This topping out ceremony marks an important milestone, as the project continues to move forward on time and on budget thanks to the entire McCarthy team.”
The expansion addresses the capacity need for women and infant care, including labor, delivery, postpartum and a new neonatal intensive care unit for babies who need extra care. In addition to women’s services, the expansion includes added space for inpatient cancer care by Banner MD Anderson Cancer Center, more space for surgical, emergency, endoscopy and imaging services, as well as shelled space for future growth.
In the final phase of the project, two new surface parking lots will be constructed, adding approximately 492 new parking spaces for visitor and staff use, and approximately 40,000 square-feet of additional renovation work is also planned within the existing medical center.
Construction on the tower expansion began in February 2021 and will complete in first quarter of 2023 with the campus renovation work completing in 2024. Banner expects to add more than 600 new jobs once the facility is opened.
The project is being managed using a modified Integrated Project Delivery (IPD) with the owner, design team, general contractor and trade partners all co-locating in a virtual “big room” allowing for the project’s design and construction strategies to be developed and enhanced through a robust system of collaboration, solution innovations and coordination strategies being brought to the project to ensure operational excellence and end-user efficiency.
Some of the innovative cost- and time-saving measures on the Banner Gateway project include:
- Prefabrication of construction elements including exterior skin, bathroom pods and mechanical and plumbing components;
- Project delivery completed in five separate design packages, allowing construction to start prior to design-phase completing;
- Construction of building expansions on three sides of the hospital that are occurring simultaneously.
As part of the IPD process, all the major building trade partners were contracted early in design to aid in target value design, constructability and Building Information Modeling (BIM) coordination prior to permit. This has proven to save on costs and ensures that the construction team is able to proceed with procurement and system fabrication earlier on in the project.
The architect on the project is SmithGroup with civil engineering led by Dibble Engineering and structural engineering led by PK Associates. Field Verified is serving as an exterior skin consultant. Major trade partners include AmFab Steel, MKB, AROK, Buesing Excavation, Delta Electric, Foothills Fire, KT Fab, Otis Elevators, Stafford Crane, SwissLog, TD Industries and Walters & Wolf.
McCarthy completed the initial Banner Gateway Medical Center campus in only 20 months in 2007.
About Banner Gateway Medical Center
Banner Gateway Medical Center in Gilbert, Arizona, offers emergency care, surgery, women’s services, obstetrics and medical/surgical beds. Banner Gateway shares the campus with Banner MD Anderson Cancer Center and is part of Banner Health, a nonprofit health care system with 30 hospitals in six states. For more information, visit bannerhealth.com/gateway.
About McCarthy
McCarthy Building Companies, Inc. is the oldest privately held national construction company in the country – with more than 150 years spent collaborating with partners to solve complex building challenges on behalf of its clients. With an unrelenting focus on safety and a comprehensive quality program that span all phases of every project, McCarthy utilizes industry-leading design phase and construction techniques combined with value-add technology to maximize outcomes. Repeatedly honored as a Best Place to Work and Healthiest Employer, McCarthy is ranked the 13th largest domestic builder (Engineering News-Record, May 2021). With more than 5,000 salaried employees and craft professionals, the firm has offices in St. Louis; Atlanta; Collinsville, Ill.; Kansas City, Kan.; Omaha, Neb.; Phoenix; Las Vegas; Denver; Dallas, Houston; and San Diego, Newport Beach, Los Angeles, San Francisco, San Jose and Sacramento, Calif. McCarthy is 100 percent employee owned. More information about the company is available online at www.mccarthy.com or by following the company on Facebook, Twitter, LinkedIn and Instagram.